Construction and Maintenance of Water Distribution Pipelines

Previous
Next
Scope of work:

1.Installation, Testing & Commissioning of HDPE lines
2.Interconnection with existing lines
3.Emergency line repair works. (HDPE, GRP & DI pipelines)
4.Construction of chambers, thrust blocks, Directional drilling, etc.

Location: Umm Al Quwain, Ajman, Dibba, Fujairah, Ras Al Khaimah, and Dhabid

Completed

Total Pipeline Layed in UAE of various sizes from DN 100 to 1800
Dhaid : 733 Kilometers
Ras Al Khaimah: 362 Kilometers
Dibba : 231 Kilometers
Umm Al Quain: 132 Kilometers
Ajman: 130 Kilometers
Total Pipe Layed in UAE: 1583 Kilometers

Construction of Pumping Station

Previous
Next
Scope of work:

1. Civil Work Construction of Pump Room
2. Pumps and motors up to – 200KW
3. Installation, testing & commissioning of the Pump room
4. Lamination and DI piping work inside the pump
5. Installation of Control Valve and Fittings for Pipeline 6.Supply and installation of the electrical connection for the Pump Room


Location: Dibba

 

Repair, Replacement & Maintenance of Water Tanks

Previous
Next
Scope of work:

1.Grit blasting & protective coating of Tank & towers
2.Repair/replacement of Tanks
3.Repair/replacement of pipelines
4.Tank cleaning, Valve changing, Level indicator / Level transmitter, repair, etc.

Location: Northern Emirates

160 MM X 1 WAY Direction Drilling HDPE Pipe Crossing

Previous
Next
Scope of work:

1. Surveying and Preparation of drawings
2. Monitoring of 160 mm Transco and 600 mm dolphine line
3. Trial pit to check existing utilities and for entry and exit pit
4. Directional drilling around RM 38 around rocky soil carefully with the locator

Location: Showkha

 

Design, Supply & Construction of Plant Internal Road

Previous
Next
Scope of work:

1. Plant internal road, footpath & car parking. Approx.: 16KM
2. Supply, install, testing & commission control cables. – 20KM
3. Supply and installation of UPVC duct lines. – 10KM
4. Road Markings, Traffic Sign Boards, etc.
5. GRP Water lines – 2KM, fire hydrant lines, protection barriers, etc.


Location: Ajman Power Plant

Construction and Maintenance Work

Previous
Next
Scope of work:

1. 600 mm dia ac piping for (underground cable ducting), coal hopper, conveyor tunnel, transformer building, silo
2. Reclaimer, kiln, cooler, ducts, preheater, cement mill, conveyors – maintenance works
3. Brick lining, cladding, silo cleaning, equipment erection, structural steel & wear-resistant steel works
4. Construction of raw water tank, product water tank, cooling water tank, pump house, transformer building & control room
5. Complete construction of pump house, raw water tank, cooling water tank, potable water tank, bore well pumps and piping and 5.5 km 200 dia ac pipeline, valve chamber, pump connection control building, etc.

Location: Cement Plant in Fujairah

Construction of Chemical Lab

Previous
Next
Scope of work:

1. Chemical resistance tile fixing in central laboratory
2. Gas piping working in central laboratory
3. Fabric partition
4. Hvac – ac ducting system

Location: Ajman

Aluminum Work

Previous
Next

Desalination Plant

Previous
Next

Location: Ajman

Construction and Maintenance of Water Distribution Pipelines in Umm Al Quwain, Ajman, Dibba, Fujairah, Ras Al Khaimah, and Dhaid

Scope of work:

1.Installation, Testing & Commissioning of HDPE lines
2.Interconnection with existing lines
3.Emergency line repair works. (HDPE, GRP & DI pipelines)
4.Construction of chambers, thrust blocks, Directional drilling, etc.

Completed: 

Total Pipeline Layed in UAE of various sizes from DN 100 to 1800
Dhaid : 733 Kilometers
Ras Al Khaimah: 362 Kilometers
Dibba : 231 Kilometers
Umm Al Quain: 132 Kilometers
Ajman: 130 Kilometers
Total Pipe Layed in UAE: 1583 Kilometers

Construction of Pumping Station in Dibba

Scope of work:

1.Civil Work Construction of Pump Room
2.Pumps and motors up to – 200KW
3.Installation, testing & commissioning of the Pumproom
4.Lamination and DI piping work inside the pump house

5.Installation of Control Valve and Fittings for Pipeline

6.Supply and installation of the electrical connection for the Pump Room

 

Repair, Replacement & Maintenance of Water Tanks in the Northern Emirates

Scope of work:

1.Grit blasting & protective coating of Tank & towers
2.Repair/replacement of Tanks
3.Repair/replacement of pipelines
4.Tank cleaning, Valve changing, Level indicator / Level transmitter, repair, etc.

 

160 MM X 1 WAY Direction Drilling HDPE Pipe Crossing in Showkha

Scope of work:

1. Surveying and Preparation of drawings
2. Monitoring of 160 mm Transco and 600 mm dolphine line
3. Trial pit to check existing utilities and for entry and exit pit
4. Directional drilling around RM 38 around rocky soil carefully with the locator

 

Design, Supply & Construction of Plant Internal Road in Ajman Power Plant

Scope of work:

1. Plant internal road, footpath & car parking. Approx.: 16KM
2. Supply, install, testing & commission control cables. – 20KM
3. Supply and installation of UPVC duct lines. – 10KM
4. Road Markings, Traffic Sign Boards, etc.

5.GRP Water lines – 2KM, fire hydrant lines, protection barriers, etc.

 

Construction and Maintenance Work in a Cement Plant in Fujairah

Scope of work:

a. 600 mm dia ac piping for (underground cable ducting), coal hopper, conveyor tunnel, transformer building, silo
b. Reclaimer, kiln, cooler, ducts, preheater, cement mill, conveyors – maintenance works
c. Brick lining, cladding, silo cleaning, equipment erection, structural steel & wear-resistant steel works
d. Construction of raw water tank, product water tank, cooling water tank, pump house, transformer building & control room

e. Complete construction of pump house, raw water tank, cooling water tank, potable water tank, bore well pumps and piping and 5.5 km 200 dia ac pipeline, valve chamber, pump connection control building, etc 

Previous
Next

Construction of Chemical Lab in Ajman

Scope of work:

1. Chemical resistance tile fixing in central laboratory
2. Gas piping working in central laboratory
3. Fabric partition
4. Hvac – ac ducting system

Aluminum Work

Previous
Next

Ajman Desalination Plant

  • 18

    Years Of Experience

  • 650

    Workforce

  • 5000

    Projects Completed

Our Branches

 

Ras Al Khaimah 

Ajman

Sharjah

Umm Al Quwain

Dibba

Copyright © 2023 Bilad Al Sham Construction and Development LLC. All Rights Reserved. | Designed and Developed by Mighty Warners Technology L.L.C.